Full Works for DHB Doughty

The Dover Harbour Board (DHB) Tug was dry docked on 10/10/2011 for a range of inspections and maintenance.

The work on the Tug included the inspection and maintenance of Main Engines including removal of Injectors for test and overhaul, function test and calibration of Engine Alarms and Safety Devices, Camshaft Deflection Measurements.

The DHB Doughty Vessel was Ultra High Pressure washed to remove marine growth, and was then primed and painted to specification. Aquamaster units were also inspected and overhauled.

After all works were completed the vessel was undocked on 15/10/2011.